Project Highlights
Client: Nuclear Power Corporation of India Ltd. (NPCIL)
Project: Nuclear Island Mega EPC Package (NIMEP) for Kaiga-5&6 Project.
Capacity: 2 x 700 MWe PHWR.
Location: Karwar Taluka, Uttara Kannada District, Karnataka State.
Type of Reactor: Pressurised Heavy water Reactor (PHWR)
Duration: 66 months for Kaiga unit-5 72 months for Kaiga unit-6
Regulator: Atomic Energy Regulatory Board (AERB)
Scope of Work
Engineering, Design, Supply, Inspection, Testing, Packing, Forwarding, Transportation to Site, Guarantee, Storage, Fabrication, Civil works, Erection, Examination, Testing, Commissioning, Operation and Maintenance as per the tender specification of Nuclear Island Mega EPC Package (NIMEP) for Kaiga-5&6 Project.
Client
Nuclear Power Corporation of India Ltd. (NPCIL)
Length in Km
Sample..
Pavement Classification
Sample..
| Role /Type | Details Type |
| EPC Contractor | M/s. Megha Engineering & Infrastructures Limited |
| Independent Engineer | M/s ALTINOK Consulting Engineering Inc., in JV with M/s SA Infrastructure Consultants Pvt Ltd & association with M/s Marsway Engineering Consultancy & Construction Service Pvt Ltd. |
| Agreement Date | 1st May 2023 |
| Appointed Date | 12th Feb 2024 |
| Maintenance Period | 15 Years after commencing |
| COD Construction Period | 24 Months (730 days) from Appointed Date |
| Project Cost | Rs. 622.94 Crores |
| Structures Scope Details | ||
| Sl. No | Type of Structure | Scope (In Nos) |
| 1 | Box Culverts /Structures | 87 |
| 2 | VUP | 5 |
| 3 | LVUP | 3 |
| 4 | Minor Bridges | 17 |
| 5 | Major Bridges | 2 |
| Total - Structures | 114 | |
| 6 | Tunnel(M) | 340 M |